-X TO OVERWORLD WORLDBORDER
This project's purpose was to extend the western highway to the overworld worldborder. This highway was the last cardinal to be paved to the overworld worldborder. This project was divided into 2 phases.
This highways is paved from spawn -> 3.75M nether (overworld worldborder)
Phase 1 (floor)
Start date: November 17th 2024
Completion date: Febuary 6th 2025
Obsidian placed: 10.530.000
Workers: ChiefBeefLoko & SwisherSurgeon
Phase 2 (railings)
Start date: May 16th 2025
Completion date: June 16th 2025
Obsidian placed: 4.960.000
Workers: Deci, CJ (qsmk), Lysenko, TullyBob, Ba4n & ChiefBeefLoko
+Z TO OVERWORLD WORLDBORDER
This project's purpose was to extend the southern highway to the overworld worldborder. This highway was third cardinal to be fully paved to the overworld worldborder.
This highways is paved from spawn -> 3.75M nether (overworld worldborder)
Start date: March 25th 2025
Completion date: April 26th 2025
Obsidian placed: 16.500.000
Workers: Yikyu, Ba4n, musheck, MasterMind, themoon, ChiefBeefLoko, OffsetPanda701, Mauricey
-Z TO OVERWORLD WORLDBORDER
This project's purpose was to extend the northern highway to the overworld worldborder. This project was divided into 2 phases.
This highways is paved from spawn -> 3.75M nether (overworld worldborder)
Phase 1 (2 wide highway)
Start date: August 30th 2024
Completion date: November 30th 2024
Obsidian placed: 5,510,000
Workers: MasterMind, musheck, Ba4n, Orange Dot, Karra itsMainlane, _2xx
Phase 2 (full width)
Start date: January 17th 2025
Completion date: February 25th 2025
Obsidian placed: 10,940,000
Workers: musheck, Ba4n, Orange Dot, OffsetPanda701
Total obsidian placed: 16,450,000
Digging Diamonds
The goal of this project was to dig 125k,250k & 500k diamond roads. Reddit Post
Start Date: May 2, 2023
Completion Date: May 14, 2023
Netherrack Mined: 98.000.000
WIDENING OF 50K DIAMOND HIGHWAY
This project was aimed at widening the already existing 50k diamond highway. The 50k diamond highway were 5 blocks wide diagonally. Now, they are 7 blocks.
Start Date: December 30, 2022
Completion Date: January 28, 2023
Obsidian Mined: 400,000+
GRID
The goal of this project was to build a big ringroad at spawn. The roads are seperated by 5k blocks in 50k blocks radius. Reddit Post
Start Date: December 3, 2022
Completion Date: February 16, 2023
Netherrack Mined: 46,247,274
Obsidian Used: 16,411,481
HWU SPAWN LOGO
The HWU spawn logo was the biggest obsidian symbol in 2b2t when it was finished. This was possible after the completion of the Nether Spawn Excavation Project. The project was started on September 11, 2021.
Completion Date: March 9, 2022
Obsidian Used: 28,168,285
WIDENING OF THE DIAGONAL HIGHWAYS
The goal of this project was to widen the diagonal highways.
Completion Date: March 9, 2022
DIAGONAL HIGHWAYS TO 1M
This project was started to extend to diagonal highways that already ended at 128k to 1m.
Completion Date: May 28, 2021
X+ HIGHWAY TO THE WORLD BORDER
After extending the main axis highways was the next plan to extend the x+ highway to the world border. This means extending the highway to 3.75m.
Completion Date: May 28, 2021
50K DIAMOND HIGHWAY
The 50k diamond highway is a ring road where the corners are located at 50k blocks away from spawn in the main axis highways. This highway cosses the diagonal highways at 25k blocks from spawn.
Completion Date: February 7, 2021
MAIN AXIS HIGHWAYS TO 1M
The goal here was to extend all the main axis highways originating from nether spawn all the way to 1m.
Completion Date: December 14, 2020
DIAGONAL HIGHWAYS TO 125K
This project's purpose was to upgrade and extend the diagonal highways to 125k. This project was begun by IIS but then was forwarded to us.
Completion Date: October 21, 2020
Obsidian Used: 800,000+